In short
If you are going to build, remodel or relocate anything connecting to the AAA’s potable water or sanitary sewer system, Chapter 9.6 of the Joint Regulation governs. Everything is filed through OGPe’s Unified Information System before the permits are granted, and the regulation adopts the technical specifications the AAA requires. There is a fast route many people can use: the Recomendación Vía Certificación, available for new construction not exceeding six equivalent units — that is, projected consumption not over 2,400 gallons per day and not requiring a meter larger than one inch in diameter — provided the connection point is close by and the laterals reach it without affecting other lots; and for remodelling that does not change the use or increase consumption, with evidence of the existing service and a registered account no more than two years old. But that route only speeds up the construction permit: it does not exempt you from the AAA’s processes during construction, and the final connection requires the AAA’s final endorsement for the Permiso Único, which includes payment of impact fees and delivery of as-built plans.
What is it?
It is Chapter 9.6 of Joint Regulation No. 9473, "Aqueduct and Sewer Works". Its provisions apply to aqueduct and sewer works carried out independently or as part of building something else. For those projects, the technical specifications in force required by the Aqueduct and Sewer Authority are adopted, including every element, requirement and technical detail in the latest versions of the regulations and codes promulgated by the AAA and adopted by OGPe. The chapter deals with potable water and sanitary sewer; it does not touch electricity.
Who can do it?
The Recomendación Vía Certificación — the fast route — is conditional. For new construction: not exceeding six equivalent units, that is, projected consumption not exceeding 2,400 gallons per day and not requiring a meter larger than one inch in diameter; the connection point to the AAA’s potable water and sanitary sewer infrastructure being close enough not to require off-site works; and the water and sewer service laterals reaching the connection point without affecting other lots. For remodelling of existing structures: the proposed action representing no change of use, no increase in projected consumption and no increase in the equivalent-unit computation; the structure being served by a meter of equal or smaller diameter than the existing one; evidence of the existing service and registered account no more than two years old; no increase in meter diameter and no new services or laterals required; the sanitary discharges being domestic and not process discharges; and reuse of the existing laterals, having made sure they are in adequate condition.
Requirements
- Filing through OGPe’s Unified Information System (SUI), before the applicable permits are granted.Verified against the official source
- Meeting the technical specifications in force required by the AAA, under the regulations and codes promulgated by the Authority and adopted by OGPe.Verified against the official source
- For the Recomendación Vía Certificación: that the proponent certifies the action qualifies, making sure the connection to the AAA’s pipes is viable and the systems can take the additional impact.Verified against the official source
- Informing the AAA of the start of the construction work.Verified against the official source
- Not segmenting applications: each project is filed and evaluated as a whole.Verified against the official source
- Carrying out the works under an Inspector designated by the project owner, who renders at least one monthly inspection report with a copy to the AAA.Verified against the official source
- For the connection: obtaining the AAA’s final endorsement for the Permiso Único, which includes payment of impact fees and other applicable charges and delivery of as-built plans and works completion reports.Verified against the official source
Documents you need
Cost
Step by step
Step 1: What falls under this chapter
The chapter’s provisions apply to aqueduct and sewer works carried out independently or as part of building something else. And for those projects the technical specifications in force required by the AAA are adopted: every element, requirement and technical detail in the latest versions of the regulations and codes promulgated by the Authority and adopted by OGPe. That is: the technical rule is not in the Joint Regulation — it is in the AAA’s codes, and the Joint Regulation adopts them.
Step 2: The six filings that go through the SUI
The regulation lists six filings that must be made through OGPe’s Unified Information System before the applicable permits are granted. First, the Infrastructure Works Recommendation, Plan Approval and Plan Amendment Approval Request, covering three things: construction of aqueduct or sanitary sewer works proposing to connect to the AAA’s system — including, without limitation, potable water distribution systems, sanitary collection systems, pump stations, wells and tanks; relocation of existing water or sanitary sewer infrastructure; and improvements to water or sanitary sewer systems. Second, the Recomendación Vía Certificación Request. Third, the Non-Domestic Sanitary Discharge Authorisation Request. Fourth, the Significant Users Sanitary Discharge Permit Request. Fifth, the Bulk Discharge Permit Request. And sixth, the Pretreatment Installations Authorisation Request.
Step 3: The recommendation request: three documents
Every recommendation request on aqueduct or sewer works must include three things. Site plans including the project’s location and a reference point with Lambert coordinates, preferably North American Datum 1983, a 1:2,000 parcel plan with reference points or a survey plan, and a sketch or location map with road number, kilometre and current reference places. Detail on the project’s scope and its elements. And, if the project is to be developed in stages, a work programme with each stage’s start and end dates.
Step 4: The construction permit is the professional’s job
The construction-permit list is long and written for the responsible engineer or architect, not the owner. It asks, among other things, for the digital plan file in DXF format with a polygon georeferenced to NAD 83; sealed and signed plans covering the connection to the AAA’s systems, the relocation or extension of works and the installations to be transferred to the Authority; hydraulic and structural calculations; a detailed analysis of any mechanical system; the licensed professional’s certification that the design concept conforms to the recommendations obtained in the pre-consultation or through the Recommendation Request to OGPe, with a copy of the documents OGPe issued; a topographic plan referenced to Mean Sea Level and a grading plan; and a geotechnical study meeting Section 5.1.2.2 on landslide-risk and other subsoil-condition analysis. The plans must also illustrate twelve classes of existing conditions in the area, from true north to rights of way, and — if the infrastructure is transferred to the AAA — carry seven notes the Authority requires. We do not transcribe the full list here: it is in the regulation and it is the signing professional’s responsibility. And one zoning detail: permits and authorisations in historic sites and zones, plazas de recreo and surrounding blocks — the towns’ founding centres — require the recommendation of the Instituto de Cultura Puertorriqueña.
Step 5: The fast route: six units, 2,400 gallons, one inch
This is the part most people can use. The applicant may file with OGPe the Recomendación Vía Certificación Request provided it meets the requirements for that filing. For new construction projects, conditional on three things: not exceeding six equivalent units, that is, projected consumption not exceeding 2,400 gallons per day and not requiring a meter larger than one inch in diameter; the connection point to the AAA’s potable water and sanitary sewer infrastructure being close enough not to require off-site works; and the service laterals, for both potable water and sanitary sewer, reaching the connection point without affecting other lots.
Step 6: The fast route for remodelling
For remodelling projects on existing structures, the certification is conditional on six things: the proposed action representing no change of use, no increase in projected consumption and no increase in the equivalent-unit computation; the existing structure being served by a meter of equal or smaller diameter than the existing one; evidence of the existing service and registered account, no more than two years old; no increase in meter diameter and no new services or laterals required; the sanitary discharges being domestic, not process discharges; and the existing water or sanitary sewer laterals being reused, having made sure they are in adequate condition.
Step 7: What the fast route does NOT save you
The regulation warns bluntly: the Recomendación Vía Certificación is granted to speed up obtaining the construction permit, but under no circumstances should this be read as exempting you from the processes required during the construction phase, as established by the AAA, leading to eventual final acceptance and authorisation to connect to the Authority’s systems. In addition, the proponent must certify the proposed action qualifies, making sure the connection to the AAA’s pipes is viable and the systems can take the additional impact; must include with the request the filing documents the AAA requires; and must inform the AAA of the start of construction. If, on checking and reviewing the certified plans and documents, the Authority notices any irregularity, deficiency, omission or error, the professional who certified the plans and the project owner are notified, and that makes it necessary to file the project again through OGPe by the conventional recommendation-request route. And one rule that forecloses a trick: the proponent must not segment applications; each project is filed and evaluated as a whole.
Step 8: If the plans must be amended
Construction plans for aqueduct or sanitary sewer works previously certified may be amended before or after the works begin, provided the professional files the amendment request through OGPe’s electronic filing system; the plans must meet the same requirements and follow the same procedure as the original request. But one case forces you back a step: if the amendments include changes in projected water consumption or sanitary discharge, the proposed load or other changes affecting the connection conditions, a new Recommendation Request must be filed before filing the amendment. And in every case, the alteration or change proposed in the amendment may not be carried out until OGPe approves the requested amendment.
Step 9: The inspector and the monthly report
Every construction project for which plan approval was required must be carried out under an inspector designated by the project owner, who must see that the works are built to the approved plans. The inspector prepares inspection reports for the various stages built and gives a copy to the AAA; each report carries observations, comments and detail on the works’ progress. At least one monthly report is due, and if no construction took place in the period concerning aqueduct and sewer works, that must be reported too. Every sheet is sealed and signed by the owner-designated inspector, thereby certifying that the inspections and tests stated were inspected and performed by them and meet the AAA’s requirements; and they must not include in the report any inspection or test they did not perform or supervise. Every inspection request must state the stretches, elements and tests to be validated by the AAA and include the corresponding certified reports; the AAA may provide a model format with the minimum information.
Step 10: The connection: the final endorsement and the Permiso Único
This is the last stretch. The owner-designated inspector or the authorised professional must file certified inspection reports with the AAA as the works progress, and the AAA reserves the right to inspect with its own authorised personnel. Every request to connect a project to be served by the aqueduct and sewer systems must be preceded by the AAA’s final endorsement for the Permiso Único, under that entity’s procedures, which includes, among other things, payment of impact fees and other applicable charges, and delivery of as-built plans and works completion reports. Once OGPe issues a Permiso Único — after the AAA’s final endorsement and the inspector’s certification that the works comply with the plans, regulations and applicable laws, and any other certification or requirement previously set by the Authority — the owner or authorised representative may request, through OGPe, that the AAA connect the project for service. Where the works include infrastructure to be maintained or operated by the AAA, the documents for its transfer, conveyance and warranty must be filed and the applicable rights of way constituted.
Step 11: And what happens if the works do not match the plans
The regulation closes with two sentences worth keeping in mind. The first favours the project: the AAA will connect the project to its system without delay, unless it finds deficiencies that put life, safety or property at risk. The second is the reverse: in every case where the AAA finds the built work departs from the plans, regulations and applicable laws certified before OGPe, it must start the corresponding administrative process and refer the case immediately to the Planning Board’s Audit and Compliance Office.
Where to do it
The chapter’s six filings are made through OGPe’s Unified Information System (SUI), before the applicable permits are granted, and plan amendments through OGPe’s electronic filing system. The AAA issues the final endorsement for the Permiso Único, receives the inspection reports and ultimately makes the connection; and the connection request is made through OGPe. Permits and authorisations in historic sites and zones and in the towns’ founding centres also require the recommendation of the Instituto de Cultura Puertorriqueña.
How long it takes
What to do if something goes wrong
First of all, check whether your project fits the fast route, because it changes the whole process. For new construction: no more than six equivalent units — projected consumption not exceeding 2,400 gallons per day and no meter larger than one inch — a nearby connection point that does not force off-site works, and laterals that reach it without affecting other lots. For remodelling: no change of use, no increase in consumption or equivalent units, a meter of equal or smaller diameter, evidence of the existing service and a registered account no more than two years old, no new laterals, domestic discharges and reuse of the existing laterals in adequate condition. If you fit, remember that route only speeds up the construction permit: the AAA’s processes during construction continue, and if the Authority finds an irregularity, deficiency, omission or error in the certified plans, the project must be filed again by the conventional route. If you do not fit, the construction permit requires a plan set signed by a licensed professional, with a DXF file georeferenced to NAD 83, calculations, a geotechnical study under Section 5.1.2.2 and a topographic plan; that is not something an owner prepares. During the works you need an inspector you designate, with at least one monthly report, a copy to the AAA, and no tests included that they did not supervise. And to connect: first the AAA’s final endorsement for the Permiso Único — which includes payment of impact fees and other charges, plus as-built plans and completion reports — then OGPe’s Permiso Único, and then the connection is requested through OGPe. If you are amending plans and the change touches consumption, discharge or the connection conditions, a new Recommendation Request must be filed before the amendment, and you may not carry out the change until OGPe approves it. Four caveats: we publish no cost because the chapter fixes no amount, although it mentions payment of impact fees and other applicable charges; we publish no timeframe because the chapter sets no terms; we do not transcribe the full plan-requirements list, which is written for the responsible professional and lives in the regulation; and the file the Board links is named "Reglamento Conjunto de Emergencia", but the document inside is Joint Regulation No. 9473 of 16 June 2023.
Common mistakes
- Believing the Recomendación Vía Certificación exempts you from the AAA’s processes during construction.
- Segmenting the project into several applications instead of filing it as a whole.
- Exceeding the six equivalent units, the 2,400 gallons per day or the one-inch meter and still using the certification route.
- Filing a remodelling through certification with service evidence and an account more than two years old.
- Failing to inform the AAA of the start of construction.
- Carrying out a plan change before OGPe approves the amendment.
- Amending consumption or discharge without first filing a new Recommendation Request.
- Signing inspection reports including tests the inspector neither performed nor supervised.
- Requesting the connection without the AAA’s final endorsement for the Permiso Único.
Frequently asked questions
What is the Recomendación Vía Certificación?
It is a route the applicant may file with OGPe to speed up obtaining the construction permit for aqueduct or sewer works, available for new construction projects not exceeding six equivalent units and for remodelling that does not change the use or increase consumption, under the conditions the regulation details.
What are six equivalent units?
The regulation explains it in the same sentence: that projected consumption does not exceed 2,400 gallons per day and that no meter larger than one inch in diameter is required.
Can I connect without the AAA’s endorsement?
No. Every request to connect a project to be served by the aqueduct and sewer systems must be preceded by the AAA’s final endorsement for the Permiso Único, which includes among other things payment of impact fees and other applicable charges and delivery of as-built plans and works completion reports.
Can I relocate an existing line?
Relocation of existing water or sanitary sewer infrastructure is one of the filings made through OGPe’s SUI. And the plans must clearly specify any proposed relocation: one plan is required for the relocation design and another for the proposed infrastructure, with the relocation plans illustrating the proposed line’s profiles.
What if the works do not comply with the plans?
The AAA will connect the project without delay unless it finds deficiencies that put life, safety or property at risk. And in every case where it finds the built work departs from the plans, regulations and laws certified before OGPe, it must start the corresponding administrative process and refer the case immediately to the Planning Board’s Audit and Compliance Office.
Official sources
These are the government pages this guide is based on.
- Oficina de Gerencia de Permisos (OGPe)
OGPe
docs.pr.gov
- Permit Management Office
ogpe
ogpe.pr.gov
- Aqueduct and Sewer Authority
aaa
www.acueductos.pr.gov
Last verified
September 4, 2026
MiPRFácil is an independent informational website and is not affiliated with, endorsed by, or operated by the Government of Puerto Rico or any government agency.
MiPRFácil does not submit applications on your behalf.
Was this guide helpful?
Did you find out-of-date information?
How to apply for the Permiso Único (single business permit) in Puerto Rico
What the Permiso Único is, which endorsements it consolidates, how to apply through the Single Business Portal, and what usually delays it.
Impact fee: who pays it, who is exempt and how to dispute it
Three presumptions of no impact, exemptions including renewable energy, and a reclassification procedure with 60- and 20-day terms.
The septic system permit for a home
What OGPe asks to authorise a septic tank, the inspection before covering, and who answers for prior contamination.
How to activate water service or put it in your name with AAA
The three routes to request water service: the Mi Acueductos portal, the (787) 620-2482 phone center and AAA’s offices.
The construction permit: what it asks for and why yours may not be “ministerial”
One permit covers urbanization, construction and demolition. If it is ministerial it moves fast; OGPe publishes exactly what disqualifies it.