In short
The obligations section of the works chapter is the densest. Article 1374 binds the principal to three things: pay the price of the work; provide the collaboration necessary for the work to be carried out; and receive the work where it has been executed as agreed. And it adds a rule many people do not know: those who put their labour and materials into a work at a lump-sum price have an action against the principal up to the amount the principal owes the contractor when the claim is made. Article 1375 binds the contractor to ten: execute the work as agreed and according to the knowledge the relevant art, science or technique requires; not vary the agreed work, except where the modifications are necessary to execute it according to the rules of the art and provided they were unforeseeable at the time of contracting; provide the principal with essential information on the execution; communicate any necessary variation and its estimated cost; warn about the bad quality or unsuitability of the materials the principal supplied; supply, save agreement to the contrary, the materials ordinarily used; execute the work within the agreed time or within the time that reasonably corresponds; allow the principal, provided it does not harm the progress of the works, to verify at its own cost the state of progress and the quality of the materials and works; guarantee the soundness of the work against ruin for a term of ten years from delivery, where it has been built on an immovable and must be of long duration — with the promoter bearing the same liability, and the architect answering if the ruin is due to defects of the soil or of the direction; and guarantee that the work serves the intended purpose.
What is it?
They are Articles 1374 and 1375 of the Civil Code of 2020: the principal’s three duties, the direct action of those who put in labour and materials, and the contractor’s ten duties, including the ten-year warranty against ruin.
Who can do it?
Principals and contractors of a work under the Puerto Rico Civil Code, and those who put their labour and materials into a work contracted at a lump-sum price.
Requirements
- From the principal: pay the price, collaborate as necessary for the work to be carried out, and receive it where executed as agreed.Verified against the official source
- From the contractor: execute as agreed and according to the knowledge the relevant art, science or technique requires.Verified against the official source
- From the contractor: communicate any necessary variation and its estimated cost.Verified against the official source
- For the action in the last paragraph of Article 1374: to have put labour and materials into a work at a lump-sum price, and that the principal owe the contractor something when the claim is made.Verified against the official source
Documents you need
Cost
Step by step
Step 1: What the principal owes
Article 1374: pay the price of the work; provide the collaboration necessary for the work to be carried out; and receive the work where it has been executed as agreed. Note the condition on the third: receive it where it was executed as agreed.
Step 2: Those who put in labour and materials may claim from the owner
The last paragraph of Article 1374: those who put their labour and materials into a work at a lump-sum price have an action against the principal up to the amount the principal owes the contractor when the claim is made. Three conditions in one line: labour and materials, lump-sum price, and the cap of what is owed at the moment of the claim.
Step 3: Executing with skill and not changing the work
Article 1375(a) and (b): execute as agreed and according to the knowledge the relevant art, science or technique requires; and not vary the agreed work, except where the modifications are necessary to execute it according to the rules of the art and provided they were unforeseeable at the time of contracting.
Step 4: Informing, and warning before changing
Subsections (c) and (d): provide the principal with essential information on the execution, and communicate any necessary variation and its estimated cost. The estimated cost is not optional: it is in the text.
Step 5: If the owner supplied bad materials, they must be told
Subsection (e): warn the principal about the bad quality or unsuitability of the materials they supplied. That warning reappears later in the chapter: if the work is destroyed because of those materials and the contractor warned in time, the principal must pay the full agreed price.
Step 6: Ordinary materials are supplied by the contractor
Subsection (f): supply, except where otherwise agreed, the materials ordinarily used in the execution. It runs in the same direction as the presumption in the price article.
Step 7: The time, even where none was agreed
Subsection (g): execute the work within the agreed time or within the time that reasonably corresponds. With no date in the contract there is still a period: the reasonable one.
Step 8: The principal may verify progress
Subsection (h): allow the principal, provided it does not harm the progress of the works, to verify at its own cost the state of progress and the quality of the materials used and the work done. Two conditions: no harm to the works, and at the principal’s cost.
Step 9: The ten-year warranty against ruin
Subsection (i), the section’s most important: guarantee the soundness of the work against ruin for a term of ten (10) years from delivery, where it has been built on an immovable and must be of long duration. Both conditions — built on an immovable and of long duration — are in the text, and the Code defines neither, nor the word "ruin".
Step 10: Who else answers for ruin
The same subsection: the promoter of the work bears the same liability, and the architect answers if the ruin is due to defects of the soil or of the direction. Those are the three figures the article names; this guide adds none other.
Step 11: And that the work serve its purpose
Subsection (j), short and far-reaching: guarantee that the work serves the intended purpose. Being built is not enough: it must serve what it was intended for.
Where to do it
These obligations are performed between the parties: the Code names no agency. Claims, including the one in the last paragraph of Article 1374 and the ten-year warranty, are litigated in the Court of First Instance. Permits, works certification and contractor registration run through other entities with their own rules and their own guides here.
How long it takes
What to do if something goes wrong
If the contractor asks for more money for changes, see subsection (d) of this article and also the rescission guide, which carries the twenty per cent threshold and a five-day period. If the work was destroyed, that is the ineffectiveness guide. If you are asking whether the contractor had to be registered or the work needed a permit, that is other legislation with separate guides. This article does not define "ruin" or "long duration", names no professionals beyond the promoter and the architect, and fixes no claiming period beyond the ten years it itself establishes. MiPRFácil does not represent anyone in court and gives no legal advice.
Common mistakes
- As the principal, refusing to receive a work executed as agreed.
- As the principal, withholding the necessary collaboration and then complaining of delay.
- As the contractor, varying the work where the modification is neither necessary under the rules of the art nor unforeseeable at contracting.
- As the contractor, making a necessary variation without first communicating its estimated cost.
- As the contractor, using bad materials supplied by the principal without warning them.
- As the principal, inspecting in a way that harms the progress of the works, or expecting the contractor to bear the cost of verification.
- Counting the ten-year warranty from signing rather than from delivery.
- Extending the ten-year warranty to works not built on an immovable or not meant to be of long duration.
- As a worker or supplier, claiming from the principal more than the principal owes the contractor at the moment of the claim.
- Believing a finished work is enough: it must also serve the intended purpose.
Frequently asked questions
How long does a construction warranty last?
Article 1375(i) requires the contractor to guarantee the soundness of the work against ruin for a term of ten years from delivery, where the work was built on an immovable and must be of long duration.
Does anyone else answer besides the contractor?
The same subsection says the promoter of the work bears the same liability, and that the architect answers if the ruin is due to defects of the soil or of the direction.
The contractor changed things without warning. Could they?
Article 1375(b) forbids varying the agreed work except where the modifications are necessary under the rules of the art and were unforeseeable at contracting; and subsection (d) requires communicating any necessary variation and its estimated cost.
The contractor did not pay the workers. May they claim from me?
Article 1374 says those who put their labour and materials into a work at a lump-sum price have an action against the principal up to the amount the principal owes the contractor when the claim is made. That is the cap the statute fixes.
Official sources
These are the government pages this guide is based on.
- Poder Judicial de Puerto Rico
Poder Judicial
bvirtualogp.pr.gov
Last verified
September 9, 2026
MiPRFácil is an independent informational website and is not affiliated with, endorsed by, or operated by the Government of Puerto Rico or any government agency.
MiPRFácil does not submit applications on your behalf.
Was this guide helpful?
Did you find out-of-date information?
The contract for works: who is the contractor and who the principal
The contractor binds itself, without being subordinate, to carry out a material or intellectual work for a price. It picks the means and may use assistants.
The price of works: who fixes it and who supplies the materials
Absent agreement, a lump sum is presumed and the contractor supplies the materials. With no price and no applicable usage, the court determines it.
The work collapsed, someone died, or it became impossible: what gets paid
Where the contract fails, the principal pays for usable materials and the proportional value of what was executed. With its own rules if the work is destroyed.
Getting out of a works contract: the 20%, the five days, and what you pay
If necessary changes raise the price by 20%, the principal may rescind — but only within five days. And they may always cancel by paying for work done.
Your project’s inspector and contractor: what they must certify
The contractor’s sworn certification, the inspector’s monthly report, the ten days to replace them and the involuntary-acquirer rule.
Contractor registry: how to check it before you sign
Act 146-1995 creates a public Contractor Registry at DACO, with bond and certification. What to demand before hiring and how long you have to claim.