Last reviewed: September 5, 2026VerifiedOGPe

In short

Rule 3.7.1 of Joint Regulation No. 9473 sets the Permiso Único’s deadlines, and they are the figures that cost the most when overlooked. The permit runs one to three years, as requested. The renewal is filed no less than forty-five days before the expiry date; filed after that limit but before expiry, an additional payment may be required, and a permit whose renewal was filed before expiry stays in force until the final determination issues. Filed after expiry, an additional charge must be paid, and the renewal can only be processed while no more than two years have passed since expiry: after those two years a new permit must be applied for. Moreover, the determination authorising a Permiso Único becomes ineffective if the use is not established within one year. The renewal covers only the certifications and licences, not the uses or the environmental compliance, unless new uses are added, and it is neither reviewable nor appealable except as to an amendment to the use. A change of name or owner is transferred automatically if six conditions are met, and the transfer gives no new term.

External link

Go to the official site

You'll leave MiPRFácilOpens in a new tab

docs.pr.gov

What is it?

It is Rule 3.7.1 of Chapter 3.7 of Joint Regulation No. 9473, in its Sections 3.7.1.1 to 3.7.1.5: what the Permiso Único includes, which documents a new application needs, how long it lasts, how it is renewed and how it is transferred on a change of owner. This site already has a Permiso Único guide written from what OGPe publishes on permisos.pr.gov — what it is, which endorsements it bundles and how to file in the Single Business Portal; that guide carries none of the regulation’s deadlines. This one is the regulation’s text.

Who can do it?

Every new or existing building with non-residential uses obtains the Permiso Único to start or continue operating. The permit is issued by OGPe, by Autonomous Municipalities with Hierarchy I to III and by Authorised Professionals; one issued by an Authorised Professional is subject to the limits of Section 2.3.1.2 of Volume II. The permit may issue where the use is ministerial or where a use variance was previously authorised. And anyone holding a current use permit must file a Permiso Único application when seeking an amendment or a name change, or if any of their certifications or licences expires.

Requirements

  • Filing the renewal application no less than forty-five days before the Permiso Único’s expiry date.Verified against the official source
  • Establishing the authorised use within one year from the date of issue: after that year, the final determination that authorised the permit becomes ineffective.Verified against the official source
  • If the permit has expired: applying for renewal before two years have passed since expiry and paying the additional charge set by OGPe’s Assistant Secretary by Administrative Order.Verified against the official source
  • Filing the renewal in the SUI under the permit’s same case number, which stays the same across every renewal, and certifying that the use conforms to the Permiso Único.Verified against the official source
  • For a transfer on a change of name, owner or successor: filing the Permiso Único application in the new owner’s name, making the payment, producing the current Permiso Único, producing evidence of title or a lease, and the authorised use continuing to be of the same nature.Verified against the official source

Documents you need

Cost

Check the current cost with the official agency.

Step by step

  1. Step 1: What the permit bundles and who issues it

    Every new or existing building with non-residential uses obtains the Permiso Único to start or continue operating, and the permit includes the uses; the Categorical Exclusion Certification or the applicable environmental document; the Fire Prevention Certification; the Health Licences; and any other applicable licence or authorisation the regulation requires for the activity. It is issued by OGPe, by Autonomous Municipalities with Hierarchy I to III and by Authorised Professionals. Inspections needed for those certifications and licences, after the permit issues, may only be carried out by personnel of OGPe, the Fire Bureau, the Department of Health, the Government Entities Concerned or Authorised Professionals.

  2. Step 2: What a new application asks for

    Besides the application Rule 2.1.9 of Volume II requires, every new application must bring four things. An explanatory memorial stating the use sought and its nature, the number of employees, the parking to be provided, the hours of operation and any other additional pertinent information. Any other licence or authorisation required for the operation. A sketch of the installation including the area of the premises or structure to be occupied, the internal layout, the location relative to the access road, the parking to be provided and the dimensions. And photographs of the installation in digital format, of the interior and the exterior.

  3. Step 3: The term: one to three years, and the year to establish the use

    The Permiso Único runs one to three years, as requested. The uses it authorises do not lapse while the commercial activity continues under the use permit issued, and renewing them is not necessary: what is renewed are the certifications and licences the permit contains. The approval resolution for discretionary cases runs one year. And there is a deadline that often surprises: any final determination authorising a Permiso Único becomes ineffective if the authorised use is not established within one year from the date of issue.

  4. Step 4: The forty-five days, and the two years of grace

    The renewal application is filed no less than forty-five days before the expiry date; if it is not sought, the permit lapses on that date. If filed before expiry but with less than forty-five days’ notice, an additional payment may be required. The important part: any Permiso Único whose renewal was filed before its expiry is deemed in force until the final determination issues. If the application is filed after expiry, an additional charge set by OGPe’s Assistant Secretary by Administrative Order must be paid, and the renewal may only be processed while no more than two years have passed since expiry. If more than two years have passed, a new permit must be applied for. The renewal is filed in the SUI under the permit’s same case number, which stays the same across every renewal.

  5. Step 5: The reminder e-mail is not a right

    The SUI may send a warning e-mail to orient and remind original applicants that the expiry date is approaching. The regulation is explicit about what that e-mail is not: it is entirely at OGPe’s discretion, without constituting or being interpreted as a requirement or an obligation for the terms to be effective or uninterrupted, and its non-sending or non-receipt will not be used as an excuse or argument for not complying with any requirement. Put another way: the calendar is the business’s responsibility.

  6. Step 6: What the renewal covers and what it does not

    The renewal is for the certifications and licences the permit contains, exempting the uses and the environmental compliance determination unless new uses are added. It carries no fresh evaluation of the already authorised use and requires no prior inspection, though the government entity concerned must inspect to verify the licences and certifications match what was authorised. The requirements are four: completing the application in the SUI and paying the charges and fees; the owner or operator certifying that the use conforms to the Permiso Único; where it does not, proceeding as the section itself provides; and complying with what the Licences and Certifications volume requires, including the renewal of the health and fire-prevention licences. The regulation closes the list with a sentence worth knowing: "No additional requirements to those established in this Section will be sought." And the renewal is neither reviewable nor appealable, except where an amendment to the use is authorised, and then only as to the amendment.

  7. Step 7: If the inspection finds uses the permit does not cover

    If the inspection identifies uses or activities not conforming to the Permiso Único, the licences or the certifications, but which are ministerially permitted in the qualification district where the property sits, in terms of use and parameters, an amendment to the Permiso Único must be sought to add the activity. Approval of that amendment is conditioned on paying the charges and fees applicable to the added use corresponding to the year before the renewal. And before filing, the fines or charges for having operated those uses without authorisation must be paid. If no amendment is sought, those uses or activities must be eliminated.

  8. Step 8: Change of owner: automatic transfer with six conditions

    On a change of name, owner or successor, OGPe, the Authorised Professional or the Autonomous Municipality with Hierarchy I to III makes the transfer of the Permiso Único automatically, provided six things are met: filing the Permiso Único application; making the transfer request in the new owner’s or successor’s name; making the corresponding payment; producing the current Permiso Único; producing evidence of title or a lease; and the authorised use continuing to be of the same nature. The body making it notifies the other agencies and municipalities concerned. A point that decides purchases: the change of owner and transfer give no new term; the permit keeps the same terms and dates as the one being transferred. And if the Permiso Único is not current but is valid, or if the change concerns a Permiso de Uso, evidence that the business was operating must be included. A name-change application requires no new environmental compliance application.

  9. Step 9: The sanctions and the flood zones

    For those in contempt of or rebellion against final orders issued by OGPe, electric or running-water service may be suspended, besides a fine of no more than one thousand five hundred dollars; and where the person or entity keeps operating without the corresponding permit, an additional fine of one thousand dollars per day may be imposed. Separately, the Permiso Único for projects in flood zones must meet the requirements of the Regulation on Special Flood-Risk Areas, the current Planning Regulation No. 13; and on Especially Protected Rustic Land or in FEMA-designated risk areas, where circumstances put health and safety at risk or adversely affect the environment, FEMA’s Flood Certification and Elevation Certificate may be required.

Where to do it

The Permiso Único and its renewal are filed in OGPe’s Unified Information System (SUI), at permisos.pr.gov, under the same case number across every renewal. It is also issued by Autonomous Municipalities with Hierarchy I to III and by Authorised Professionals, the latter subject to the limits of Section 2.3.1.2 of Volume II of the regulation. The late-renewal charge is set by OGPe’s Assistant Secretary by Administrative Order, which the regulation does not reproduce.

How long it takes

Check the current processing time with the official agency.

What to do if something goes wrong

Four dates decide nearly everything. The first: the use must be established within one year of the permit’s issue, or the final determination becomes ineffective. The second: the renewal is filed no less than forty-five days before expiry; filed later but before expiry, an additional payment may be required, though the permit stays in force until the final determination. The third: once expired, there are two years to renew by paying an additional charge; after those two years, renewal is over and a new permit must be started. And the fourth, the one forgotten when buying a business: the transfer gives no new term — the permit arrives with the same dates it had. If the inspection turns up activities the permit does not cover but the district permits ministerially, they are added by amendment, paying first the fines for having operated them. And do not count on the SUI’s reminder e-mail: the regulation says expressly that its non-sending or non-receipt is no excuse.

Common mistakes

  • Letting the year to establish the use pass and losing the final determination that authorised the permit.
  • Filing the renewal with less than forty-five days before expiry and running into the additional payment.
  • Letting more than two years pass since expiry: renewal is no longer possible, a new permit must be sought.
  • Waiting for the SUI’s reminder e-mail as if it were a mandatory notice.
  • Buying a business thinking the permit’s transfer restarts the term.
  • Seeking the transfer when the authorised use is no longer of the same nature.
  • Not including evidence that the business was operating when the permit is not current but is valid.
  • Operating activities the Permiso Único does not cover and not seeking the amendment before the inspection.
  • Filing the amendment without first paying the fines or charges for having operated those uses without authorisation.
  • Filing a new application without the explanatory memorial, the sketch or the interior and exterior photographs.
  • Counting on appealing the renewal: it is neither reviewable nor appealable, except as to an amendment to the use.
  • Renewing in the SUI by opening a new case instead of using the permit’s same case number.

Frequently asked questions

How long does the Permiso Único last?

It runs one to three years, as requested. The approval resolution for discretionary cases runs one year. The authorised uses do not lapse while the commercial activity continues under the use permit issued; what is renewed are the certifications and licences.

How far in advance must you renew?

No less than forty-five days before the expiry date. If filed before expiry but with less than forty-five days, an additional payment may be required. And any permit whose renewal was filed before its expiry is deemed in force until the final determination on the application issues.

My permit expired — can I still renew it?

Yes, while no more than two years have passed since expiry, paying the additional charge set by OGPe’s Assistant Secretary by Administrative Order. If more than two years have passed, a new permit must be applied for.

How is the permit transferred when buying a business?

The transfer is automatic if six conditions are met: filing the Permiso Único application, making it in the new owner’s or successor’s name, making the payment, producing the current Permiso Único, producing evidence of title or a lease, and the authorised use continuing to be of the same nature. The transfer gives no new term: the permit keeps the same terms and dates.

Can the renewal be appealed?

The Permiso Único’s renewal is neither reviewable nor appealable, except where an amendment to the use is authorised; and for amendments to the use, review may only be sought as to the action or activity the amendment contemplates.

What happens if I operate without the permit?

For those in contempt of or rebellion against OGPe’s final orders, electric or running-water service may be suspended and a fine of no more than one thousand five hundred dollars imposed; and where the person or entity keeps operating without the corresponding permit, an additional fine of one thousand dollars per day may be imposed.

Official sources

These are the government pages this guide is based on.

Last verified

September 5, 2026

MiPRFácil is an independent informational website and is not affiliated with, endorsed by, or operated by the Government of Puerto Rico or any government agency.

MiPRFácil does not submit applications on your behalf.

Was this guide helpful?

Did you find out-of-date information?

Did you find out-of-date information?

No account needed. We don't ask for personal data.