In short
Section 2.1.8.7 of Joint Regulation No. 9473 creates a little-known and very useful service: the Pre-Consultation Request. Any person interested in a permit, licence, certification, authorization, recommendation or any process needed to operate a business in Puerto Rico may request from OGPe or the autonomous municipality with hierarchy I to III an orientation identifying the legal and regulatory provisions applicable to the proposed action, activity or project, and the information they will have to file in due course. More concretely still: the applicant may require the agency to provide a list of the permits or authorizations they must obtain to begin the project’s construction or operation. The Permit Managers and the Director of the Environmental Compliance Evaluation Division or their representatives take part in the evaluation, at the discretion of the Assistant Secretary or the Regional Director. The applicant includes in writing and in detail, at a minimum, the proposed location and a description of the project. The answer is given in writing and, together with what the applicant filed, is available for public examination in the SUI, unless confidentiality is claimed and justified for containing business secrets. Two limits matter: the Pre-Consultation is subject to payment of the applicable charges, and although it may include recommendations, it is in no case considered a final determination on approving or rejecting the project.
What is it?
It is the first of the services Section 2.1.8.7 of Joint Regulation No. 9473 makes available to the public in the SUI, apart from permit applications proper. The Pre-Consultation neither approves nor denies anything: it serves to clarify, before filing, which requirements and exemptions apply to the project, and which permits will need to be obtained.
Who can do it?
It may be requested by any person interested in a permit, licence, certification, authorization, recommendation or any process needed for or bearing in any way on a business’s operation in Puerto Rico, before OGPe or the autonomous municipality with hierarchy I to III, as applicable.
Requirements
- Including in writing and in detail, at a minimum, the proposed location and a description of the project.Verified against the official source
- Paying the applicable charges: the Pre-Consultation process is subject to that payment.Verified against the official source
- To claim documents’ confidentiality: justifying it for containing business secrets that may not be disclosed, and paying the additional charge that may be required for handling the process.Verified against the official source
- For Pre-Consultations included in Rule 3.2.4 item (c) on works exempt from construction permits: an Explanatory Memorial with location data, cadastre number, footage, a detailed description of the work, materials where applicable, volume or quantity where applicable, and calification.Verified against the official source
- For those same Pre-Consultations: a sketch or photos of the area to be impacted, and for interior wall changes, a sketch of the existing and proposed layout.Verified against the official source
Documents you need
Cost
Step by step
Step 1: What may be asked
Any person interested in a permit, licence, certification, authorization, recommendation or any process needed to operate a business may request an orientation identifying the legal and regulatory provisions applicable to the proposed action, activity or project, and the information the applicant will have to file in due course. One need not be an owner nor have the project designed in order to ask.
Step 2: The list of permits
The section’s most practical item is the second: the applicant may require the agency to provide a list of the permits or authorizations they must obtain, under the applicable legal and regulatory provisions, in order to begin the project’s construction or operation. It is a right to ask for the whole map before starting to walk it.
Step 3: Who evaluates it
The Permit Managers, the Director of the Environmental Compliance Evaluation Division or their representatives take part in evaluating the Pre-Consultation, as applicable, at the discretion of OGPe’s Assistant Secretary or Regional Director. That is, the orientation does not come from a generic counter: it is signed by the same divisions that will later evaluate the case.
Step 4: What must be filed
As part of the Pre-Consultation, the applicant includes in writing and in detail, at a minimum, the proposed location and a description of the project. That minimum is deliberately short: the more concrete the description, the more useful the answer.
Step 5: The answer is written and public
The answer from OGPe or the autonomous municipality with hierarchy I to III is given in writing, and that answer — like the information the applicant filed — is available for public examination in the SUI, unless the applicant claims and justifies the documents’ confidentiality for containing business secrets that may not be disclosed. Where confidentiality is claimed, payment of an additional charge for handling the process may be required.
Step 6: What the Pre-Consultation is not
The process is only to clarify, before any application is filed, the requirements or exemptions applicable to the project, subject to payment of the applicable charges. And although the Pre-Consultation may include OGPe recommendations, it is in no case considered a final determination on approving or rejecting the proposed action. It serves to plan, not to start the work.
Step 7: If a meeting is requested, five days
If the petitioner requested a meeting as part of the Pre-Consultation, within no more than five days of the filing date the client is notified of the required documents. A note on the source: that five-day term is stated only for the case where a meeting is requested; the section sets no term where none is.
Step 8: The Pre-Consultation for exempt works
Pre-Consultations included in Rule 3.2.4 on works exempt from construction permits, item (c), carry more paper: an Explanatory Memorial with location data, cadastre number, footage, a detailed description of the work to be done, materials where applicable, volume or quantity where applicable and calification; a sketch or photos of the area to be impacted; and, for interior wall changes, a sketch of the existing and proposed layout. OGPe or the municipality may request any additional document or information.
Where to do it
The Pre-Consultation is requested from OGPe or the autonomous municipality with hierarchy I to III, as applicable, and is processed through the SUI, where the answer and what was filed remain available for public examination unless confidentiality is claimed and justified.
How long it takes
What to do if something goes wrong
This is the tool that prevents discovering mid-build that a permit was missing. It is worth using with a concrete description — proposed location and a detailed project description are the minimum — and expressly invoking item 2: the list of permits or authorizations that will have to be obtained to begin construction or operation. If talking in person helps, requesting the meeting triggers a term: within five days of filing the required documents are notified. Two things must be clear before filing. The first is that the answer and everything submitted become public in the SUI, unless confidentiality is claimed and justified for business secrets, which may also cost an additional charge. The second is that the Pre-Consultation approves nothing: even carrying OGPe recommendations, it is not a final determination, so it does not authorize starting. And if the project falls under the works exempt from construction permits in item (c) of Rule 3.2.4, one must arrive with the complete Explanatory Memorial, sketch or photos, and, if interior walls move, the sketch of the existing and proposed layout.
Common mistakes
- Treating the Pre-Consultation as an approval, when it is in no case considered a final determination.
- Starting the work on the strength of the recommendations the answer carries.
- Filing the Pre-Consultation without the proposed location and without a detailed project description.
- Not expressly asking for the list of permits or authorizations that will have to be obtained, which is the applicant’s right.
- Submitting sensitive information without claiming and justifying confidentiality, when what is filed becomes available to the public in the SUI.
- Assuming the Pre-Consultation is free, when it is subject to payment of the applicable charges.
- Claiming confidentiality without allowing for the additional charge that may be required for handling the process.
- Filing an exempt-work Pre-Consultation without the Explanatory Memorial with cadastre, footage, materials, volume and calification.
- Omitting the sketch of the existing and proposed layout where interior walls will be changed.
Frequently asked questions
May I ask which permits I need before filing?
Yes. Any interested person may request from OGPe or the autonomous municipality with hierarchy I to III an orientation identifying the applicable provisions, and may require that they provide the list of permits or authorizations to be obtained in order to begin the project’s construction or operation.
Does the Pre-Consultation authorize starting the work?
No. Although it may include OGPe recommendations, the process is in no case considered a final determination on approving or rejecting the proposed action.
Is what I submit in a Pre-Consultation public?
Yes. The answer and the information filed are available for public examination in the SUI, unless the applicant claims and justifies confidentiality for containing business secrets that may not be disclosed; in that case an additional charge may be required.
How long until they tell me which documents I need?
If a meeting was requested as part of the Pre-Consultation, within no more than five days of the filing date the required documents are notified. The section sets no term where no meeting is requested.
Official sources
These are the government pages this guide is based on.
- Oficina de Gerencia de Permisos (OGPe)
OGPe
docs.pr.gov
- OGPe Single Business Portal
ogpe
www.permisos.pr.gov
- Planning Board
jp
jp.pr.gov
Last verified
September 7, 2026
MiPRFácil is an independent informational website and is not affiliated with, endorsed by, or operated by the Government of Puerto Rico or any government agency.
MiPRFácil does not submit applications on your behalf.
Was this guide helpful?
Did you find out-of-date information?
Filing a permit in the SUI: 10% on submission, five days to validate and the remaining 90%
The application is not deemed filed and no term runs until it is validated, and it is archived if not cured within thirty days.
Requesting a copy of a permit file, and what each SUI process is
Any interested person may obtain a copy or certified copy of the SUI’s digital and historic files.
Which works need no construction permit: painting, roof sealing, changing windows
Thirteen activities are not construction works and ten minor works are exempt, but an Exempt Works Application must be filed and municipal excise taxes paid.
Location consultation: which projects need one and what is filed
The seven situations requiring a location consultation, the commercial categories by square feet, and the process’s fifteen- and ten-day terms.
How to apply for the Permiso Único (single business permit) in Puerto Rico
What the Permiso Único is, which endorsements it consolidates, how to apply through the Single Business Portal, and what usually delays it.
Who may apply for a permit: proving you are owner, optionee or lessee
Deed, lease, purchase option, registry certification or heirship declaration: one suffices, but one is required.