Occupying a green project: the authorization that comes before the use permit

Last reviewed: August 15, 2026VerifiedOGPe

In short

The Green Project Occupancy Authorization (AOV) is requested once the Authorized Inspector certifies compliance with the requirements of the International Green Construction Code or one of the adopted reference rating systems. According to OGPe’s manual, these authorizations are issued before the granting of a Green Use Permit, in order to verify the performance and efficiency of the green project, as certified by the Authorized Green Projects Inspector. There are five requirements: holding the Green Construction Permit; the certification that the project complied with the International Green Construction Code or one of the reference rating systems; stating the type of property to be occupied, the proposed use for each floor of the building or structure and the components to be occupied; the contact information of the Works Inspector and the Green Projects Inspector; and those inspectors’ end-of-construction reports, which must be uploaded by the inspectors themselves. Seven documents are required, four of them marked mandatory: the designation contract of the Authorized Green Projects Inspector, the certification of compliance with the Code, the Service Authorization Application, the service petition and the CRIM certification, plus the location sketch and the structure sketch. And the fact that is not common in the permit system: there is no cost for this type of filing.

The manual carries no revision date in its edition and revision table, which is blank, and refers to “the reference rating systems adopted by this Chapter” without listing them. The International Green Construction Code is updated by editions. Confirm with OGPe which edition and which systems govern before contracting the certification.

External link

Go to the official site

You'll leave MiPRFácilOpens in a new tab

docs.pr.gov

What is it?

It is an intermediate step between finishing construction and being able to use the building. In an ordinary project, once the works are finished you go to the use permit. In a green project there is one more step: OGPe wants to verify the performance and efficiency of what was built before granting the Green Use Permit, and for that it relies on the certification of an Authorized Green Projects Inspector. That figure is not generic: OGPe’s professionals regulation recognises eight classes of Authorized Inspector and one of them is specifically for Green Projects. The standard it is measured against is the International Green Construction Code or one of the reference rating systems adopted by the corresponding chapter.

Who can do it?

The manual places the filing after two things: the Green Construction Permit and the Authorized Inspector’s certification that the project complied with the International Green Construction Code or one of the reference rating systems. Without those two, there is no AOV to request. The manual publishes no size threshold, use type or restriction on who may file beyond that, and this guide adds no requirement the source does not impose.

Requirements

Documents you need

Cost

There is no cost for this type of filing. The manual does not price the fees of the Authorized Green Projects Inspector or the Works Inspector, which are separate.

Verified against the official source · August 15, 2026

Step by step

  1. Step 1: Know from the outset that a green project is not ministerial

    This is not in the AOV manual but in the Consolidated Construction Permit one, and it is worth knowing before planning dates: projects classified as Green Projects will not be considered ministerial. That is, a green project’s construction permit cannot take the fast route a private Authorized Professional can sign; it follows OGPe’s regular evaluation flow, with the initial 10% charge and the remaining 90% after the analyst’s validation. Building green has benefits, but speeding up permitting is not one of them.

  2. Step 2: Designate the Authorized Green Projects Inspector by contract

    The first mandatory document on the list is the Designation Contract of the Authorized Green Projects Inspector. That inspector class is one of the eight recognised by OGPe’s professionals regulation, and the agency publishes the listing of inspectors with their credential number and expiration date. Check the credential before signing the contract, and remember the regulation forbids an inspector from certifying a project in which they participated or one belonging to a relative within the degrees it sets.

  3. Step 3: You do not upload the end-of-construction reports

    This is the detail that stalls files. Among the requirements is that the end-of-construction reports of the Works Inspector and the Green Projects Inspector be presented, and the manual specifies that those reports must be uploaded by the inspectors themselves. Even with the other six documents ready, the application is not completed until they log in and upload theirs. Coordinate it in advance and have their contact details to hand, because the manual also asks for them as a separate requirement.

  4. Step 4: Obtain the CRIM certification

    The CRIM certification is marked mandatory in the document list. It comes from another agency — the Municipal Revenue Collection Centre — so it is not something resolved the same day. Request it early, together with the location sketch and the structure sketch, the two documents the manual does not mark as mandatory but does list.

  5. Step 5: File free of charge, but within thirty days

    The manual says plainly that there is no cost for this type of filing, which sets it apart from almost everything else in the Single Business Portal. What does run is the deadline: the service application will remain open for a maximum term of thirty days for the applicant to complete it, and once that term passes without completion or without all required documents uploaded, the application process must begin again. With documents that depend on third parties — the inspectors and CRIM — that term is the filing’s real risk.

Where to do it

The Green Project Occupancy Authorization is filed in OGPe’s Single Business Portal, selecting AOV under Permits. The applicant manual is published in the Information Sources section of permisos.pr.gov, and the listing of Authorized Inspectors is in the Authorized Professional or Inspector section of the same portal.

How long it takes

Check the current processing time with the official agency.

What to do if something goes wrong

What the manual does not publish, and this guide does not invent: it does not say how long OGPe takes to issue the authorization, what happens if the Green Projects Inspector does not certify compliance, what the inspectors charge, or exactly which reference rating systems are adopted — the manual says “one of the reference rating systems adopted by this Chapter” without listing them, and that chapter belongs to a different regulation not read here. If you need to know whether your LEED or equivalent certification counts, ask OGPe before contracting. A sequence warning: the AOV comes before the Green Use Permit, it does not replace it; obtaining it does not authorise operating. And the critical point of the whole filing is the dependence on third parties: the end-of-construction reports are uploaded by the inspectors, and the CRIM certification comes from another agency. The thirty-day term runs regardless.

Common mistakes

  • Counting on the ministerial route for a green project: the PCOC manual expressly excludes it.
  • Believing the AOV replaces the Green Use Permit: it comes before it, not instead of it.
  • Opening the application before the inspectors are ready to upload their end-of-construction reports.
  • Leaving the CRIM certification to the end, being from another agency and mandatory.
  • Hiring an inspector without checking their credential and expiration date in OGPe’s listing.
  • Designating as inspector someone who participated in the project, which the regulation forbids.
  • Assuming any rating system counts without confirming which are adopted.
  • Losing the thirty-day term waiting on third-party documents.

Frequently asked questions

How much does the AOV cost?

The manual says there is no cost for this type of filing. What does cost, and the manual does not price, are the fees of the Authorized Green Projects Inspector and the Works Inspector.

With the AOV can I already occupy the building?

The manual says these authorizations are issued before the granting of a Green Use Permit, in order to verify the project’s performance and efficiency. It is a prior step, not the use permit.

Who uploads the end-of-construction reports?

The inspectors themselves. The manual says so expressly: the end-of-construction reports of the Works Inspector and the Green Projects Inspector must be uploaded by the inspectors themselves.

Official sources

These are the government pages this guide is based on.

Last verified

August 15, 2026

MiPRFácil is an independent informational website and is not affiliated with, endorsed by, or operated by the Government of Puerto Rico or any government agency.

MiPRFácil does not submit applications on your behalf.

Was this guide helpful?